Size: 2,848 Sq ft

Sector: Technology

Service: Building Consultancy

Address: Tower 42, City of London

Type: Acquisition & Dilapidations Negotiations

The client instructed SHB to advise on a Stay vs Go strategy, helping them decide whether to remain in their existing office or relocate before committing in either direction.

Challenge

The client needed clear advice on their next move while protecting their position on the space they might vacate. With dilapidations liability likely at lease exit, an evidential baseline had to be in place early, rather than at the end of the lease when the tenant’s position is typically weaker.

Actions

SHB began the Stay vs Go assessment in January 2025 and commissioned a Schedule of Condition on the existing space in February 2025 to protect the client ahead of any dilapidations negotiation. The assessment led to the acquisition of a new 2,848 sq ft suite within the same building, Tower 42, on a five-year lease with a break at year three.

Running in parallel, SHB’s building surveying team represented the client in dilapidations negotiations on the vacated space, using the Schedule of Condition recorded over a year earlier as a documented baseline. Office agency, lease advisory and building consultancy worked as one team throughout, giving the client a single point of advice across the acquisition, deposit return and exit liability.

Results

• Favourable rent agreed
• Seven months’ rent free
• Rent deposit returned in full
• Dilapidations liability reduced by £42,500 against the landlord’s opening position